Specifications include, but are not limited to: The project would consist of the installation of approximately (260) linear feet of conduit duct bank from Diversion Chamber-24 to Pump Station-17. Two parallel conduits shall be installed in a poured concrete duct bank. A portion of the work is in PennDOT right-of-way (SR3001). The project is located slightly northeast of the intersection of Broadway Street (SR3001) and North Walnut Street, Nanticoke, PA. The project will include but not be limited to excavation, core drilling of the diversion chamber structure, underground conduit, duct bank, pavement/sidewalk/curb/tree lawn restoration, traffic control, etc. All labor, tools, equipment and materials for the project shall be provided by the contractor.