Specifications include, but are not limited to: This work will consist of the rehabilitation of an existing sanitary sewer line using cured-in-place pipe (CIPP) lining of approximately 722 LF of 36” diameter terra cotta pipe. This work will also include the installation of a temporary bypass system for the sewer flows, cleaning, and closed circuit televising of the sanitary sewer lines; as well as the rehabilitation of four (4) sanitary manholes using cementitious lining, including the furnishing of three (3) new pre-cast cement concrete manhole risers. In addition, this work involves the clearing, excavation, forming and construction of a 12-inch depth cement concrete footing attached to the existing masonry manhole and prepped to receive the new pre-cast concrete manhole riser.