Specifications include, but are not limited to: 1. Construct, maintain and remove construction barriers for each construction zone. (Only one gang shower area may be under construction at any given time, unless the Owner agrees to allow more). 2. Remove and reinstall all fixtures as needed. 3. Remove the existing pre-cast epoxy/terrazzo shower pans and remove from the building. 4. Remove all existing methyl-methacrylate acrylic (MMA) floor coatings and scarify all concrete slab-on-grade surface areas in preparation of new topping slabs. ; A-Unit 2nd Floor Gang Showers – Base Bid a. Concrete Bonding Agent - Apply to scarified concrete slab at all floor areas when installing high strength repair mortar - Use specified 2-part epoxy bonding agent. b. Shower Pans, Cast-In-Place (CIP) - (nominal thickness - 2”) Use specified high strength repair mortar 1. 75 sq. ft. total c. Dry-off & Dressing area floor (CIP) - (nominal thickness - 1”) Use specified high strength repair mortar 1. 84 sq. ft. total d. Waterproof Membrane - (nominal thickness - 100 mil) Use specified elastomeric product over all floor & pan areas 1. 159 sq. ft. total ; . Cementitious Urethane Floor Coating System - (nominal thickness - 3/8”) Install on new topping slab over all floor & pan areas - Use specified floor coating system - (Gray) 1. 159 sq. ft. total f. Dry-off & Dressing Area – 4” Curb 1. 27 lin. ft. total g. 3/8” Horizontal & Vertical Grout Lines - Remove existing grout to 1/2” deep from block surface & replace with specified epoxy grout - (White) .