Specifications include, but are not limited to: reconstructing the curb alignment along the northwest side of the turnaround to allow room for the buses to successfully pass on another. This shall involve the removal of the existing curb and landscaping to install a temporary concrete turnaround approximately one thousand nine hundred square feet (1,900 sq. ft.) in area with a new curbed landscape area. Adjustments to the storm and sanitary manhole castings in the area of the disturbance are required as well. COTA does not anticipate any temporary landscaping work, other than topsoil regrading and seeing, post-construction. No storm water management is anticipated due to the temporary nature of the improvement and minimal disturbed area related to the project.