Specifications include, but are not limited to: The objective of this project is to increase safety by allowing correct distances between aircraft and taxiways, eliminate two Air Force airfield waivers, eliminate back taxi requirements, and eliminate the shut-down of the POL (petroleum fuels) road when aircraft are using Taxiway Alpha. The project’s construction will be split into two Phases with Phase 1 being the required work to meet the objective above and Phase 2 being an extension to the end of Runway 5 to make the taxiway more user friendly. Design shall consist of but is not limited to the following information: - Demolish existing 4,250 SY of Taxiways(12,750 for desired) - Construct 21,400 SY of Asphalt Pavement Taxiway (27,800 for desired) - Install required Edge Drainage, Navaids, and Lighting