Specifications include, but are not limited to: Increasing water transmission capacity to the existing Ridgeview and upcoming Kilmayne water tanks within the water system’s Central Pressure Zone by reinforcing the existing 12” water line on Kildaire Farm Road between Maynard Road and Queensferry Road. The Central Pressure Zone is the original and largest of three pressure zones in the Town. The Project will also require connecting to the Ridgeview water tank by reinforcing the water line along Cary Parkway or along High Meadow Drive. Water System Master Planning efforts have recommended that this section of water line be reinforced by installing a new 20” water line. The selected D-B team will, among other things, be responsible for confirming the adequate sizing of proposed water lines and for creating and evaluating alternatives, including evaluating whether to replace or reinforce aging AC water mains within the project limits. The Project will include design and installation of approximately 8,500 linear feet of water line along the Project route.