Specifications include, but are not limited to: The University of New Mexico PPD-Utilities Department wishes to receive proposals to remove 8” steel waterline and replace with 8” ISCO HDPE or approved equal. 480LF of 8” Steel pipe to be replaced with approximately 8” ISCO HDPE or approved equal. HDPE can be fused or mechanically fastened. Remove and replace 2 each 8” butterfly valves. 2 each taps (approximately 2”) for irrigation must be replaced in new locations. Valves are required at each. Work must be completed in two sections to minimize service disruption. Any outages must be coordinated with UNM Project Manager. If an outage is to last longer than two hours, work must be done during off hours (Evening/weekends), if outage to last longer than 12 hours a temporary/alternate water source must be provided. A 1” valved port must be installed on each section for treatment and sampling. Remove and replace approximately 100LF of 8” steel pipe. A 1” valved port must be installed for treatment and sampling.