Specifications include, but are not limited to: There is a 3-inch 50 PSI steel gas main approximately 50inches deep that is approximately parallel to the proposed water main along the north side of A Street from Sta. 102+00 to Sta. 118+00. There are no known conflicts with the gas main. Caution shall be used during parallel operations along the gas main. 2. There are gas main crossings at Sta. 121+15, 86’ Rt. and Sta. 201+14.55 on the South side of A Street. There is potential for crossing conflicts and the Contractor will need to verify the gas main elevation prior to boring and excavation operations at these locations. 3. There is a gas crossing at Sta. 127+87.72 and there is potential for crossing conflicts. The Contractor will need to verify the gas main elevation prior to excavation operations at this location.