Specifications include, but are not limited to: Room’s 100 – 113 on the front short hallway are to be painted last due to a summer camp program starting two weeks after school ends lasting for 5 days. Classrooms are to be painted first so teachers can move back into the rooms while hallways are being painted. School will be responsible for providing access to ALL areas for painting. All walls will be cleared of all materials by the school. Classrooms are to be painted first before hallways. Room’s 144 & 166 are to be excluded from the painting project; Apply sheens as defined below: Wood, Opaque: Semi-gloss Wood, Transparent: Satin Concrete, Masonry, Opaque: Eg-Shel Concrete, Masonry. Epoxy: Epoxy Semi-gloss Ferrous Metals, primed & unprimed: Semi-gloss Galvanized Metals: Semi-gloss oil base Gypsum Board, Plaster: Flat Exposed Ceilings: Flat Existing Brick: Epoxy Semi-gloss.