Specifications include, but are not limited to: 1. Re-locate electrical components. 2. Provide temporary partition to maintain corridor security. 3. Install door. C. Phase 1b: install generator docking station 1. Install generator docking station. 2. Install generator distribution panel (GDP). 3. Make wiring ready for connection to ATS’s. D. Phase 2: replace generator (anticipated construction of 1 week) 1. Provide 600kW portable generator, wire to generator docking station and make ready for emergency use. 2. Disconnect and demo generator feeder to ATS-E. (permitted occupant outage: 1 hour) 3. Connect ATS-E to GDP. 4. Re-energize ATS-E. 5. Ensure auto start controls are functioning between ATS-E and temporary generator. 6. Disconnect and demo generator feeder to ATS-S. (permitted occupant outage: 2 hours). 7. Connect ATS-S to GDP. 8. Re-energize ATS-S. 9. Ensure auto start controls are functioning between ATS-S and temporary generator. 10. Demo permanent generator. 11. Install new generator. 12. Provide wiring from new generator to GDP. 13. Install new ATS-OS. 14. Provide wiring from GDP to ATS-OS. 15. Provide normal feeder from ATS-OS to wireway above NHDP for future connection.