Specifications include, but are not limited to: • Demolition and removal of the existing original boiler, burner and breeching up to chimney • Reuse of existing boiler cement pad • Provide and install (1) Columbia Steam Boiler 30HP or equal to natural gas firing • New boiler would include ProFire Q modulating burner or equal to, linkage less controls, variable speed blowers, low and auxiliary water cutoffs, high limit and operating controls, Relief valves, CSD-1 Safety Compliant. • One year parts warranty. • New Steam piping to existing header location • New gate valve for boiler isolation • New piping insulation for new steam piping installed • Condensate piping from existing boiler feed tank to new boiler • Provide and install new B-venting for boiler to existing B-venting • Gas piping work disconnect and reconnect to new boiler with new regulator as required • Hoisting and lifting required for entire project • City, state permits and inspection of project