Specifications include, but are not limited to: The project delivery method for construction is bid-build. The Project consists of a Sequencing Batch Reactor WWTF and Effluent Disposal via Wicks servicing the Downtown Area. The design average design flow is 245,400 gpd consisting of wastewater, septage and inflow and infiltration (I/I). The initial average design flow is estimated at approximately 140,000 gpd. The septage receiving facility will have a daily average capacity of 16,500 gpd to service properties that continue to rely on septic systems. The WWTF and Effluent Disposal will accommodate the future average daily flow of 104,600 gpd from the Meetinghouse Pond Area resulting in a total annual average flow of 350,000 gpd. The WWTF is located off Overland Way, where the former Tritown Septage Treatment Facility has been demolished, and the Effluent Disposal is located off Lots Hollow Road.