The project includes the razing of some of the existing 1‐story portion of the building, maintaining the existing power plant housing the MEP equipment providing services to the adjacent 3‐ story swing space, constructing a new 1‐story addition, complete renovation of the remaining 2‐story portion of the building, all related site work, and, ultimately, the demolition of the existing power plant and the existing 3‐story swing space. All current school operations have been relocated to the adjacent March Middle School building throughout the duration of the project. The project totals 144,200 SF in size. The remaining existing building contains 100,005 SF, and the additions will total 44,195 SF. Work is anticipated to start in December of 2019. The project consists of all major and school‐type trades.