The bridge deck overlays and miscellaneous repairs work to be performed under this Contract includes the following: 1. Furnish, install, maintain, reset, and remove all Maintenance of Traffic measures as detailed in the Plans and/or as directed by the Engineer. 2. Remove existing deck joint assemblies, including portions of the existing concrete deck and concrete parapets, to the limits shown on the Plans. This work will be completed in stages (as required) across the width of the roadway. 3. Furnish and install deck joint assemblies, new compression seals, new strip seals and associated hardware. This work will be completed in stages (as required) across the width of the roadway, however, in place of the proposed compression seals, temporary foam seals shall be placed in stages across the roadway. Once the joint assemblies have been constructed across the entire roadway, the compression seals shall be installed in one piece.