Specifications include, but are not limited to: The Contractor shall remove and dispose the old boiler in its entirety. 2.2.3 The Contractor shall dispose of all construction debris and demolition materials off-site at an acceptable location. 2.2.4 The Contractor shall tie the new boiler into existing piping, gas, electric, controls and venting. 2.2.5 The Contractor shall install pipe insulation which shall match existing insulation. The Contractor shall install boiler, piping, wiring and accessories in accordance with the manufacturer’s installation instructions. 2.2.6 The Contractor shall provide materials that are compatible when installed with the boiler manufacturer’s current application requirements and with all warranty requirements. 2.2.7 The Contractor shall test and inspect operations of the boiler. 2.2.8 Installation shall meet or exceed all applicable federal, state and local requirements.