Specifications include, but are not limited to: The elevator shaft addition was constructed in 1983, while the connection addition was constructed in 1965. There is no data for when the original building was constructed but the extents of the original building are not within this project area. There are currently signs of differential settlement within the elevator addition and the adjacent stair well shaft. This project will include excavating the soil next to the south wall of the elevator shaft, and installing 3 micropile adjacent to the concrete stem wall. After the micropiles are installed, a concrete grade will be constructed to connect the existing stem wall construction to the micropiles for support. After the installation of the micropiles and grade beam, the area will be backfilled with appropriate fill per the earthwork specification. After the foundation repair is complete, the rest of the project includes tuck pointing brick veneer, replacing expansion joints in masonry walls and concrete slabs, removing and re-caulking wall to adjacent interfaces, and stabilizing beam bearing pockets.