The Project consists of 2” water main replacement on NW Paramore St. and in the alley West of NW Jackson St, as shown on the included Project Drawings. The intent of this project is to replace approximately 290 Lineal Feet of 2” PVC water main. The Project will also include miscellaneous water main appurtenances and the removal and replacement of concrete sidewalk. The estimated quantities of this main replacement project are: 1. Install 5/8” or 1” Meter, Meter Pit, and Top 4 EA; 2. 1” Service Line 81 LF; 3. 2” Water Line, HDPE SDR-9 290 LF; 4. 2”x1” Tapping Saddle and Corp Stop 4 EA; 5. Make Connection to 2” PVC Water Line 1 LS; 6. Remove and Replace 4” Concrete Sidewalk 180 SF; 7. Inlet Protection 1 EA; 8. Seeding, Fertilizing and Mulching 0.1 AC; 9. Traffic Control 1 LS; 10. Construction Staking 1 LS; 11. Compaction Testing 1 LS; 12. 1” Blowoff 1 EA