Specifications include, but are not limited to: The resulting Dredged Material (along with lake water) will be transported via a temporary pipeline to the Property. Once deposited in the Storage Site, the Dredged Material will separate from the lake water, and excess water will be pumped back to Black Hawk Lake via a temporary pipeline. Temporary equipment will be stored and operated on the Storage Site and Staging Area. The specific equipment used is at the discretion of the dredging contractor, but typically consists of diesel powered pumps, excavators, bull dozers, skid loaders, watercraft, trucks and trailers. Working hours at the Storage Site could be 24-7. Upon completion of the project, the DNR shall restore all terrestrial disturbances to pre-construction conditions.