Specifications include, but are not limited to: 4.2.1 Contractor shall provide all labor and materials for exterior, interior, and ceiling framing on the 6th Floor of the Veterans Memorial Building per drawings provided as Attachments E, F, and G to this RFB. 4.2.2 The framing package shall include all gyp board on interior walls, exterior walls and ceiling. 4.2.3 Blocking shall be included as shown on the drawings, Attachments E, F, and G. 4.2.4 Contractor shall provide insulation of interior walls. A separate future bid will include insulation of exterior walls with spray foam. 4.2.5 Job progression will create a gap of time between framing and wall blocking, and gyp installation for electrical and plumbing. This gap needs to be considered for bid pricing and schedule.