Specifications include, but are not limited to: The 2020 Pavement Rehabilitation Program will focus on the main campus at 1215 Houbolt Road, Joliet, IL. The project will include parking lot S6 and the entrance drive from Houbolt Road. Parking Lot S6 will require a small amount of storm sewer work to address a chronic drainage issue. This will include an inlet, manhole with frame and grates and approximately 132 feet of 12” RCP storm sewer. Restoration of patching in the parking lot will be required. The S6 parking lot improvements will include the removal of 2 inches of existing bituminous parking lot, adjusting storm sewer inlets, patching base as needed, installation of leveling binder and new surface constructed. The parking lot will need to be painted to match the current parking lot layout. All signage will need to be placed to match existing.