Specifications include, but are not limited to: The scope of work includes the items shown below; some items are owner furnished and some are bid as alternates. • Disassemble and relocate chiller #4 • Re-assemble chiller #4 • Relocate the electrical transformer and switchgear • Provide and install new cooling tower(s) and structural steel support framing on the existing concrete pier(s) • Provide and install new variable speed condenser water pump • Provide and install new variable speed primary chilled water pump • Provide a new structural housekeeping pad for the chiller • Extend existing chilled water header and make piping connections to new and relocated equipment • Provide and install electrical wiring, conduit and equipment connections • Provide and install new controls to interface with the existing plant