Specifications include, but are not limited to: The OCIDA seeks proposals to establish contract services necessary for, and incidental to performing all operations in connection with furnishing, delivery, and installation of plants (also known as "landscaping”). 1. Locate, purchase, deliver and install all specified plants. 2. Water all specified plants. 3. Mulch, fertilize, stake, and prune all specified plants. 4. Maintenance of all specified plants until the beginning of the warranty period. 5. Plant warranty. 6. Clean up and disposal of all excess and surplus material. 7. Maintenance of all specified plants during the warranty period. 1. Installation of all plants must be completed between JANUARY 2, 2019 and MARCH 1, 2019.If Contractor begins planting on January 2, 2019, completion must occur within 60 days. If Contractor begins planting on January 17, 2019, completion must occur within 45 days.