Specifications include, but are not limited to: 1. Prepare a draft Project Execution Plan summarizing the project goals and objectives; the Design-Builder project approach; project organization requirements defining resources/staffing plan, responsibilities, contacts, and communication plan; Design-Builder’s quality assurance/quality control (QA/QC) plan; project budget, schedule and work breakdown structure; financial tracking procedures; and scope change management process. The project delivery schedule shall be in coordination with County’s requirements and milestone dates. Submit for review within 14 calendar days following written Notice to Proceed. 2. Schedule and facilitate a Project Kickoff Meeting with County and Program Manager within 21 calendar days following written Notice to Proceed.