Specifications include, but are not limited to: 3.1A Coil Railcars • Loading Timeframe: 30-40 minutes per railcar • 70,000 lbs. coil (Max) • 45,000 lbs. coil (Avg.) • Load 1 coil at a time • Load 4-6 coils per railcar • Crane operators must move mobile crane multiple times (3 times avg.) per railcar Crane vendor must supply: • Crane vendor must provide 2 x 10’ polyester round slings (90,000 lbs. vertical lifting capacity / sling each), • Crane vendor must provide 1 x 16’ steel wire cable (9 x individual ½” cables) (79,500 lbs. basket lifting capacity) (sourced from Port City Industrial) 3.1B Bar Railcars • Loading Timeframe: 45-60 minutes per railcar • 14,000 lbs. bar (Max) • 12,900 lbs. bar (Avg.) • Load 2 bars at a time • Load 13-17 bars per railcar GPA supplied: • GPA will supply 1 x 20’ spreader bar (requires signed letter of indemnity) • 5’ endless slings (sourced from steamship line).