Specifications include, but are not limited to: . The base scope of the Project consists of the replacement of select water-source heat pumps throughout the building. Heat Pump Replacements and Temporary Cooling Units: 1. All ducted units are to be demolished, removed from site, and made active to produce cooling and heating during one overnight shift. 2. All console units are to be demolished and removed from site in batches of no more than three (3) at any one time to allow the related architectural renovations to be performed. Temporary cooling units of equal capacity are to be provided by the contractor for any occupied duration while permanent console units are out of service. 3. Temporary cooling units may remain in place of any permanent console units for no more than three (3) weekdays. 4. Temporary cooling units are to be discharged to plenum space above ceiling. Contractor to remove and reinstall ceiling materials as needed to faciliate installation and removal.