Specifications include, but are not limited to: 1 Install 8" PVC Sanitary Sewer Pipe, 0' - 4' Deep, complete. LF 130 2 Install 6" PVC ‘wye’ fitting on 8" Sanitary Sewer Mainline, complete. EA 1 3 Install 6" Sanitary Sewer Lateral Pipe, 0' - 4' with bends and connectors, complete. LF 20 4 Install New Sanitary Sewer Manhole, 0' - 4' Deep, complete. EA 1 5 Connect 8" PVC mainline sewer pipe to existing manhole, complete. EA 1 6 Install 8” PVC inside drop in existing MH with maintenance ‘Tee’ section, complete. EA 1 7 Rock excavation, complete. CY 40 8 Excavate unsuitable material, complete. CY 10 9 Install gravel backfill in place of rock and/or unsuitable material, complete. CY 40 10 Trained flagman (other than Police). /HR 24 11 Place temporary hot mix pavement 2’ thick in trench, complete. LF 140 12 Cut and plug 12” storm pipe in trench, complete. EA 2