Specifications include, but are not limited to: Project A consists of removing and hauling all existing asphalt to a depth of 3” to 7” and to include removal of 0.1’ of existing subgrade, installation of fly ash soil stabilization material to a depth of 12” andto include all compaction and repaving the street section with 1 -4” bottom mat of HBP and 1- 3” top lift of HBP. The Bid shall consist of furnishing all labor, materials, and equipment necessary to completesoil stabilization and HBP installation to those streets listed on the Location Schedule in the Specifications, or as directed by the City Project Representative. More specifically, this project shall consist of applicable traffic control, valve/manhole adjustments, asphalt removal from paved existing roadway, installation and compaction of soil stabilization (flyash) and placing hot bituminous pavement.All roadway cross slopes shall be set at a two percent minimum and three percent maximum.