The project will add 2 pre-fabricated cantilever roof structures, one on each side of the University Center loading dock area. This will be critical to keep employees and the Rocket Composter out of the snow/ice, while making the loading dock area safer and less exposed to the elements. The Rocket Composter requires a roof over it for operations and will be installed after the roof has been completed.
-Install Coverworx cantilever roof structures on both sides of the University Center loading dock. (Purchased by WCU)
-Pour concrete/rebar footings
-Erect the pre-fabricated Coverworx structures
-Install metal seam roof on both sides
-Paint as needed
(Referenced attached drawings)
Project Start Date: Spring 2019 (April 1) End Date: May 1, 2019
The contractor will be responsible for pouring the concrete/rebar footings, erecting the pre-fabricated steel roof structures on both sides of the loading dock, installing the metal seam roof, any painting or touch up painting required, and a minor amount of groundwork or landscaping in the area around the foundation.
Western will be responsible for removing any irrigation and landscaping prior to the contractors start of work. Also, Western will dig the holes for the footers on both sides of the loading dock. Western will also be responsible for adding any irrigation and landscaping back to the area after the contractor is finishing with installation.
- All contractors must be in compliance with the The Colorado Wage Act (C.R.S. 8-4-101 et seq.), Colorado Minimum Wage Order 34, and the Federal Fair Labor Standards Act.
- All contractors, including prime and sub-contractors, must be bonded and insured.