The work to be done by the Contractor shall consist of removal and replacement of sidewalks, pedestrian ramps, curb and gutter, curb returns, patterned concrete, asphalt paving, removal of existing traffic control equipment, installation of new underground conduit, electric service, j-boxes, traffic signal equipment and removal and replacement of pavement markings. The work also includes installation of a new storm sewer system which will tie into the existing Grant Park Channel along with 2 water line relocations in order to construct the storm sewer in the proposed location. This work shall include restoration of all areas disturbed by the construction activities to a condition better than the pre-construction condition, and the protection or replacement of all fencing, retaining walls, landscaping, removal of obstructions, minor utility relocation and/or adjustment, grading, soil scarification, moisture control, backfill & compaction and plantings. The project location is the intersection of Meadowland Blvd and Westwood Blvd. The intersection is heavily used by PEDs and school traffic for US Grant Elementary. The coordination of school and traffic phasing will need to be considered when placing bids.
Westwood Blvd is scheduled to be milled and overlaid with the 2018 paving program, so the project schedule is of upmost importance to the City and will be expected to be withheld. The project must be completed no later than 105 calendar days from Notice to Proceed.