Colorado Mountain College’s Leadville Campus located at 901 South Highway 24, Leadville, Colorado is requesting quotes from qualified firms and/or individuals to construct the Get Outdoors Leadville (GOL!) Gear Library, an outdoor gear library for the local Leadville community. The gear library will be a freestanding pre-engineered metal building of approximately 2,000 SF for the purpose as a storage building with restrooms, small residential kitchen, and offices. The building will be adjacent to Colorado Mountain College’s (CMC) existing Climax Building on the campus in Leadville, Colorado.
SPECIFICATIONS
The General Contractor’s scope of work will generally consist of the following, in addition to the terms of a CMC modified State of Colorado Construction Manager/General Contractor Agreement (State Form SC-6.4).
1. General
a. Regularly attend in person Owner and Design Team meetings during all phases of design and construction.
b. Promote the use of local labor and resources at all available opportunities.
2. Preconstruction
a. Provide milestone cost estimate updates at 100% DDs and 100% CDs
b. Perform interim pricing exercises for alternate design solutions, as required
c. Provide on-going value engineering guidance to the design team
d. Competitively bid all work on the project
e. Agree to execute a final GMP at any stage of design at and after 100% DD.
f. Conduct a GMP process in a completely fair and transparent manner.
g. Candidate must demonstrate commitment to and ability to work with local subcontractors to obtain as many local bids on the project as possible.
h. Work closely with NV5 and Design Team to establish the project schedule, and provide regular updates as design progresses.
Schedule will include design durations
Identify long lead items and critical path tasks
Evaluate site constraints, phasing, regulatory requirements, material and equipment deliveries, and workforce availability
i. At each phase of design, review the documents for constructability and prepare a formal list of comments to be reviewed and coordinated with NV5 and the Design Team.
The sequence of construction, efficient use of materials and labor, and construction sequencing are all to be considered in this review
j. On an on-going basis, make recommendations to the design team regarding design documentation and detailing.
3. Construction
a. Construct the work according to the construction documents and specifications within the scheduled timeframe agreed to with the Owner.
b. Maintain all relevant project archive records on behalf of the Owner such as meeting minutes, as-built drawings, specifications, submittals, RFI’s, schedules and inspection reports.
c. Prepare pay applications in accordance with contract requirements and break out billings by specific scopes of work and/or by buildings, if requested by the Owner, to accommodate the Owner’s accounting system and possible multiple steams of revenue.
d. Deliver a finished project with the highest quality workmanship.
e. Maintain and be responsible for the project schedule with weekly updates for the construction team.
f. Be responsible for the construction budget and communicate budget status to the project team on a regular basis.
g. Be proactive throughout the construction to minimize punch list work at substantial completion.
h. Understand construction activities will be carried out while College activities continue near occupied buildings. Security and logistical coordination will be of high importance to the Owner. At the Owner’s request, all personnel working on the project site must provide the Owner with background check information. It will be the General Contractor’s responsibility to provide background check information for all persons who will be present on site for the general contractor, subcontractors, and suppliers. Additionally, the candidate must be aware of prohibited items by law on College properties and take proper actions to ensure these items are not brought onto school property by employees, subcontractors and suppliers under direct supervision of the Contractor.
4. Closeout Services
a. Provide warranty and closeout assistance as required in the contract documents.
TIMELINE
- Design: Release 100% Design Development: 2/21/2020
- Construction: Target Start for Metal Building Fabrication 2/24/2020 - CMC desires to engage the metal building sub-contractor and start fabrication as soon as possible.
- Design: Release 100% Construction Documents: 4/16/2020
- Permitting: Submit for Permit (with State): 4/20/20
- Start Construction: 5/25/2020
PROPOSAL CONTENT
The information provided herein is intended to assist Bidders with a proper response to this RFP. CMC believes that this RFP provides interested Bidders with sufficient information to submit proposals that meet minimum requirements. However, the RFP is not intended to limit a proposal’s content or to exclude any relevant or essential data. Bidders are encouraged to include additional information that will substantiate their service capabilities, product quality, and commitment to support your product or service. Any exceptions or alternate offerings to this request must be communicated. CMC reserves the sole right to determine what is considered to be “equivalent” or “equal”. CMC also reserves the right to request samples for testing and evaluation.
Additionally, CMC recognizes you as the expert in this industry and we appreciate ideas that may improve the design or implementation of our project. Please submit your bid to the specifications provided and include information or ideas you may have that CMC should consider to improve our project. Our selection committee will carefully review these ideas and we will contact you with questions.
Bidders shall submit the following specific information with their bid:
1. Each candidate shall prepare a fee proposal based on your proposed pre-construction and construction schedule milestones. Candidates MUST use and submit the workbook provided to submit the following electronically in Excel format:
a. FEE & TIME COMMITMENT TAB
i. Provide a Lump Sum Fee for Preconstruction Services (Reimbursable expenses are assumed to be included within the lump sum fee).
ii. Provide a Construction Services fee (OH&P) as a percentage of the Cost of the Work. At the point the Final GMP is established, the percentage fee will be calculated and converted to a lump sum Construction Service fee.
iii. Provide the Change Order Mark Up % for your firm.
iv. Provide the Change Order Mark Up % your firm will allow from subcontractors.
v. Provide your company’s Bonding Capacity
vi. Indicate the percentage of ‘contractor’s contingency’ your firm would include as part of a Final GMP assuming the Final GMP was executed at different phases of design (i.e. 100% DD or 100% CD).
vii. For each of your proposed team members, provide the amount of time they will be committed to this project, as a percentage of full-time, for each phase.
b. GENERAL CONDITIONS TAB
i. Every cell in this tab MUST be filled with a value as follows:
1. A lump sum dollar value calculated based on your proposed schedule.
2. “NO COST” representing there will be no cost for that item in completion of this project. Given the size and location of this project there will likely be a large number of line items for which “NO COST” is the correct input.
3. “COST OF THE WORK” representing that that item will not be a fixed cost, but rather a tabulated cost of the work. This option should be used very sparingly as the Owner desires to limit their risk exposure for costs that could arguably be calculated and fixed based on the durations established in your proposed schedule.
ii. For the bonding and insurance line items please assume a construction budget of $700k
c. CLARIFICATIONS & EXCLUSIONS
i. Provide any clarifications or exclusions to the fee proposal.
2. Schedule: We are asking each candidate to submit a proposed schedule they believe to be the best balance of economics, efficiency, and phasing. Preconstruction services will commence immediately upon selection through the completion of permit documents.