1. Monument Sign: Project is to create a new monument sign system at the corner of 12th Street and
Bob Adams Dr.
New sign to replace current monument sign
Sign type: One-sided freestanding
Sign features vertical CMC logo and measures 46” x 60” with arched top to match roof feature
Overall sign system to measure approximately 96” x 120”
Carved style sign fabricated from multiple layers of HDU - bronze finish with raised white logo
Support structure fabricated from steel, wood / synthetic wood (HDU) & stone
Arched roof element fabricated from aluminum tubing with MPG paint system - bronze finish
Bottom front-side of roof features recessed LED illumination strip, running entire length of roof
producing an illuminated wash on sign and columns
Fabricate two (2) stone columns; each to measures 24” x 24” x 72”
Colorado Buff strip stone veneer over CMU blocking capped with aluminum bronze plates
2. Pylon Sign Face Replacement: Project is to create a new overlay logo sign at the upper Bob
Adams Dr.
New sign face overlay to replace current logo sign
Sign type: One-sided freestanding
Sign measures approximately 33.25” x 93.5” with arched top
Aluminum sign plate finished with MPG paint system - CMC blue finish
Reverse-cut for illuminated letters - CMC yellow
Transport sign cabinet to shop for modifications
Current sign has LED illumination. Any needed upgrades to light system not included
3. Design & Sign Permit:
Final design renderings for all scopes
Prepare final designs for monument sign system and pylon sign system
Assist CMC with sign permit application forms and site plan documentation
Draft scaled drawings with call-outs & dimensions for pylon sign system
Schedule meeting with Town planner to review proposed sign designs
Submit complete package to CDD
CMC to pay all applicable permit fees
Does not include building or electrical permits (if applicable)
4. Site Work & Installation:
Pickup and delivery of all items
Demolition, removal and hauling of existing pylon sign face, removal of existing non-illuminated sign
Excavation of new trenches, haul fill dirt
Set & level structure
Pour 3000 psi concrete footers
Rough-in for new electrical conduit sleeve
Install all sign components with provided hardware (2) locations
document:
Monument Sign
$
Pylon Sign Face Replacement
$
Design, Permit Process fees
$
Delivery and Installation fees
$
Removal of Old Sign
$
Project Terms:
• Fabricated to approved drawings & specs. Price subject to change with material and design changes
• Estimate based on normal working conditions / no unusual circumstances encountered during installation
• All permit fees handled by CMC
• Any required upgrades or service performed to existing solar light system handled by CMC
• Any required upgrades or service performed to existing pylon sign light system or electronic reader board handled by CMC
• TIMELINE
Sign installations: No later than August 17th, 2018.