Specifications include, but are not limited to: The work includes the following: 1. Perform electrical service tasks a) Exercise b) Tighten c) Lubricate d) Clean 2. Perform electrical tests a) Dynamic testing of safety devices b) Thermographic imagery under load 3. Make minor corrections during each shutdown 4. Identify and document items to be corrected in future shutdowns 5. Train District staff in methods, techniques, procedures, and standards included in an advanced electrical testing program The following is a typical list of electrical equipment to be tested. The specific list of equipment is in Exhibit E of this RFP. 1. Switchgears and switchboards, 480V; 2. Transformers, dry-type, air cool, low-voltage, 480V/120V-208V-240V, up to 100kva; 3. Transformers, dry-type, air cool, low-voltage, 4160V/277V-480V, up to 1,000kva; 4. Transformers, liquid-filled, 4,160V/277V-480V, up to 2,500kva; 5. Cables, low-voltage, 600V and 2,000v rated;