Specifications include, but are not limited to: A. Saw, cut, break, and remove approximately 25’ long x 1’ wide x 2’ deep of asphalt and concrete to expose pipe. Length of excavation will be from the gas meter to the rise of building. B. Remove existing line and install new 1 1/2” gas line. New gas line to be connected to gas meter and connector to building. C. Contractor shall test the gas line to ensure no leaks, cracks, or other discrepancies are found. D. Contractor shall ensure proper inspection of the project is conducted by government entities and service providers, as needed. E. Patch excavated asphalt and concrete with asphalt and concrete. F. Keep all areas clean and free from any hazards at all times in working area, and haul away all trash, debris, and left-over soil.