Specifications include, but are not limited to: Full demolition of the existing terminal, full re-build, and additional structure beyond the original footprint size. The project is to be designed and constructed to meet LEED Platinum certification (minimum Gold) and a Net zero operation. Construction will be phased in order to keep a portion of airport operations functioning and passenger movement uninterrupted. SFIA Terminal 1 Boarding Area B Project construction value range is anticipated to be $400 million to $600 million. The Demolition/Salvage of Stage 3 scope includes, but is not limited to: The cost of all necessary labor, material, equipment, supplies, and supervision required to complete the Demolition/Salvage of Stage 3 for the SFO T1 Boarding Area B Project in accordance with the Contract Documents.