Specifications include, but are not limited to: 3.2.1. The contractor shall originate the power from the 225 Amp 208Y/120V Panel “LC2” in Building 44 Room 12. Panel Location shown in Appendix A, Figure 1 and existing panel shown in Appendix A, Figure 2. 3.2.2. Contractor shall supply and install a new 3-pole 60-Amp circuit breaker and route the new circuit south to the southern exterior of Building 44 with appropriately sized conductor in appropriately sized EMT. 3.2.3. The circuit shall run out of the building to a new wall mounted NEMA 3R 60-Amp non-fused disconnect. (Disconnect Location shown in Appendix A, Figure 1) 3.2.4. From the disconnect the contractor shall install one appropriately sized NEMA 3R gutter box and from the gutter box three (3) 3 inch HDPE conduits (HDPE must be schedule 80 and approved/listed for directional boring and electrical installations meeting the requirements of ASTM D2447/F2160/NEMA TC-7 latest editions) to the location in the northernmost aircraft sunshade column line as shown in Appendix A, Figure 3. HDPE conduit must have minimum ground cover of 48 inches. The 3 conduits shall originate from a weatherproof enclosure or pull box below the disconnect and gutterbox. The contractor may direct bury the three (3) 3-inch conduits (Schedule 80 PVC up until the point of the directional bore) up to the apron edge prior to the directional boring installation.