Specifications include, but are not limited to: This bid includes all labor, tools, equipment and material to remove the existing fueling island and install a new Locomotive Refueling Facility in the Alaska Railroad yard in Anchorage Alaska. Phase 1-Replace fueling island, September 1st 2019 to May 1st 2020. This phase will remove and replace the existing fueling island, piping and fuel arms before passenger season 2020. New refueling island shall be fully operational on existing tankage by May 1st 2020. Including; Removing and transporting to the Anchorage landfill in Eagle River 200 tons of diesel impacted concrete in the existing island. Removing and transporting to ASR on Reeves Blvd in Anchorage 150 tons of diesel impacted soil under the existing island. Tent and heat as needed to complete concrete and piping Connecting the new piping from the new island to the existing fuel piping outside of the area of the new refueling equipment tanks and pump pad. Maintaining electrical controls to the existing pump system. Phase 2-Install new fueling system, April 1st 2020 to October 1st 2020 This phase will complete the Locomotive Refueling Facility as shown on the plans Including; Removing and transporting to ASR on Reeves Blvd in Anchorage 150 tons of diesel impacted soil under the new equipment pad and truck offload area. Switching fuel piping and electrical to new system as needed