The scope of work for this project shall consist of removing and replacing brick pavers in front of the Welcome Center and down Park Street to the intersection of Choice Ave. Also replacing sewer service and tying into the manhole in Park Street. The backfilling of Park Street shall be GAB and 6 IN of HES Concrete with milled joints and asphalt overlay using 12.5 mm mix. Replace the handicap ramps per plans. All striping shall be thermoplastic with two Applications. Place additional electrical run with plugs per plans. All work shall be completed per City of Dahlonega plans dated 10/20/2023 and latest revision date of 2/13/2024. All work will be done in accordance with the 2021 standard specifications from the Georgia Department of Transportation, the Manual on Uniform Traffic Control Devices, and by the special provisions contained in the bid documents for this project.