Specifications include, but are not limited to: Providing renovations at Rowan Hall, located on the Glassboro, NJ Campus. A. This project is for the renovation of Rowan Hall to include classrooms, Information Technology closets, and other spaces in accordance with the contract documents. B. Summary of Project Milestones 1. Substantial Completion: August 1st, 2017. Work shall be substantially completed within 151 consecutive calendar days from the construction start date. 2. Final Completion: September 1st, 2017. Work shall be fully completed; including all construction punch-list work by this date. 3. Unfavorable weather conditions shall not be justification for delays in completion or final completion dates as specified. No change orders will be issued or approved for extensions of time due to weather conditions. C. Project will be constructed under a single prime general construction contract.