Specifications include, but are not limited to: Vista High School Track and Field Replacement. The scope of this project includes the demolition and replacement of the existing synthetic track and artificial turf field. New work also includes a retaining wall with drainage, new AC paving with an aggregate base, slurry coat and seal of existing AC paving. The baseball backstop scope includes demolition and removal of the existing CMU backstop & adjacent fencing, as well as portions of existing chain link perimeter fencing. New work includes the construction of (1) new CIP concrete backstop, new chain link fencing, existing bullpen relocation, and various site upgrades. All scope contained within the drawings and specifications for DSA #04-122112 and 04-122828.